LZX Production Status 2018, Updated September 27th

September 27th 2018 Update: Over 100 Vidiots were shipped in the last week, and we are continuing to build and ship through until everyone’s orders are out there. If you’re waiting on a Visual Cortex backorders, those are in assembly now as well.

August 22nd 2018 Update: Last Thursday we received our Vidiot assemblies and it’s been a frenzy of activity over here. We have a batch of 96 units we’re shooting to have in the mail before Knobcon, with the remainder of our backorders shipped later in September. Passage and Bridge restocks are nearly complete and we’re endeavoring to tie up all our other production loose ends before Knobcon. Visual Cortex assemblies should be shipping to us soon.

August 8th 2018 Update: It was a bit later than we were told, but we got word that our Vidiot assemblies have shipped today, so next week we should be able to finally resume shipments. We’re anxious and ready to get all backorders fulfilled as soon as they arrive! Passage and Bridge restock runs are getting panels and knobs this week and should all be added to stock soon.

July 27th 2018 Update: In the past week, Passage & Bridge SMT are complete and backorders began shipping, a few Vidiots shipped, funds were wired for Visual Cortex PCB assemblies at our contractor, Andor 1 basic units added to stock, and we got word Vidiot assemblies are shipping to us the first of the upcoming week. We will hopefully receive them the end of next week and then Vidiots will begin flooding out the gates the first and second weeks of August.

Originally Posted July 20th 2018: It’s busy days for us here at the LZX workshop, and we’re scrambling to keep up with production and development spread in many directions. We build niche products in very small batches by most electronics manufacturer’s terms, so when many items are out of stock at once it can bog us down for months. Couple this with our decision to transition into managing our own manufacturing and distribution in house again back in April of this year, and it’s been intense to say the least – and at times impossible to successfully gauge the fulfillment time table. It’s important that you know we haven’t forgotten any orders, and that we are working around the clock to get caught up.

We are a team of three and a quarter full time video freaks, not a large company with different departments or vast resources. We like being a small community focused shop that can focus on the specific needs of our niche customer base, and hope to stay that way. Unfortunately that means being along for the ride with us sometimes when production doesn’t go as smoothly as expected or a vast number of projects are on the table at once (currently, both of these cases are true.)

If you’re getting impatient. Please remember that we’ll gladly substitute anything we currently have in stock for what you ordered if you’d like something different. Since June 1st, we’ve ceased accepting back orders on any products we do not have in the building ready to ship, unless it is a large order from a retailer that would otherwise help push the project into production. This policy is helping us get caught up faster.

This is where we are with production as of July 20th, 2018. Please do not expect day-by-day updates to this thread, we’re too busy building stuff! We’ll try to post these updates monthly, or weekly if there’s a lot of news. This is an attempt to communicate proactively with anyone who is waiting on these items in order to reduce the amount of e-mail we get inquiring about the status of orders.

In Progress
These units are in various stages of assembly in our workshop and are expected to be either shipped to waiting backorder customers or added to our stock on the website in the near future.

  • 40x Andor 1 Basic (Black), all parts here just need to package them
  • 25x Andor 1 Deluxe (Black & Ivory), same as above
  • 20x Doorway, SMT is running next week, second half of a batch from last month
  • 40x Staircase, SMT and through hole assembly complete, waiting testing and packaging
  • 100x Passage, some units in thru hole assembly, some SMT assemblies still in review
  • 100x Bridge, first half of the SMT assemblies ran today, currently being inspected
  • 100x Vidiot, these are the units we have left from an assembly batch of 100 that didn’t go as well as we’d have liked as an in house job due to the complexity of the mainboard assembly. Since we aren’t shipping any that don’t meet up to our expectations of quality, we’ve ordered and paid for an additional 200x assemblies from a third party company. While we wait for those, we’re working through the units we built in house and testing/shipping them, it’s just very slow going – even with some extra hired hands over the past few weeks.


Vidiot assemblies in review

Waiting On Subcontracted Assembly
We have all the parts to finish these items in our workshop, but are waiting on a third party assembly company to finish their work and deliver sub-assemblies.

  • 200x Vidiot, expecting mainboard sub-assemblies to arrive in ~2 weeks, then we will mate them with rear assemblies we have waiting in house. This means we expect to have all our Vidiot orders out the door in the first half of August.


Fresh SMT assemblies for Passage and Bridge

Ready And Waiting
These production runs are currently waiting for a spot in the schedule, but are otherwise ready to go in terms of special and long lead time items such as frontpanels and through hole components. We plan to contract SMT assemblies for these units as soon as we can, but may have to space them out in series due to being stretched so thin in terms of production funding right now. Hopefully we can move a good nubmer of these to “in progress” before the end of the month. Listed here in order of production priorities:

  • 100-200x Prismatic Ray
  • 50-100x Shapechanger
  • 50-100x Visual Cortex
  • 50-100x Navigator
  • 50-100x Curtain
  • 50-100x Sensory Translator


Carts loaded with through hole components and Vidiot assemblies

Pre-Production
Your preorders for Orion series modules have been going directly into components purchasing for Memory Palace, Escher Sketch, Diver and TBC2. We had 2500 sliders and slider caps that came in this week, as well as all our switches and illuminated pushbuttons. It’s been exciting to see all the parts start arriving, and to be putting some time into finishing the project in general. We plan to begin assembly some time in September.

Thank you very much for your continuing support of the work we do here at LZX. You are an essential part of our team and are appreciated by each of us here on a personal level.

Lars

18 Likes

Making anything is so incredibly hard. Kudos for feeding our video lust.

2 Likes

already placed my order for a memory palace. thanks for all your hard work!

3 Likes

I notice preorder is now closed for shapechnager but really wanna get my hands on one. Whats the best way to ensure i get one from the scheduled production run of 50-100?

1 Like

@destroythings Just keeping an eye on the sales page and this forum for news is all we can offer right now. We used to take backorders in situations like that, but right now we’re just trying to whittle down the backorders list in general until we’re caught up. We plan to use this subforum (the LZX switchboard) to make announcements on restocks and so on – you should find an option to subscribe to updates, so that you get e-mail notifications when we post here.

3 Likes

Great update! You do amazing things.

2 Likes

Excited for the Vidiot flood. :-]

These new modules look great, but I’m still waiting for the Vidiot I ordered from Perfect Circuit back in May. Any update on when those will ship?

@northerntao Yes, if you read the original post it provides a full update. We just received the assemblies in question yesterday and are hard at work on them now.

Hey Lars! Is there a rough estimate on when the Shapechanger modules will start entering production, or is it unknown at this stage?

Shapechanger and Prismatic Ray are up next. We have both projects queued up with our CM, and all the frontpanels/other components are here and waiting.

4 Likes

Trying to get a vidiot. I keep seeing mention of backorders, but I don’t see a way to order it here. Are you referring to backorders from other retailers? If I pre-ordered from a place like Perfect Circuit, how realistic is it that I’d get in on this “vidiot flood” before they’re gone? Is there a better way?

2 Likes

We’ll be opening up for new orders shortly. Production on our current batch of 200 units is progressing rapidly, but they’re all already spoken for. We’ll open up orders at the point we’ve purchased components for the followup batch. Perfect Circuit have a large number of units on order with us so if you preorder from them now, your unit would ship ahead of one you would order from us after we open orders back up.

3 Likes

Is it possible that we could see a restock in Shapechanger by late September, early October?

Prismatic Ray assemblies have now been paid for, and Shapechanger is up next. We have both projects queued up with our CM, and all the frontpanels/other components are here and waiting. That’s the update for now.

2 Likes

Great! The order is in. Thanks!

1 Like

All Vidiot backorders are on track to be in the mail before the end of the month. We have 3 guys working full time on it right now, and it’s going great.

Regarding our exchange policy, you’d have to talk to Switched On about that. If you placed the order through us we’d be happy to do that, but in this case Switched On is our customer and the pre-sale arrangement is between you and them. I can confirm they have units on order that will be shipped soon, though!